Traffic control plan design

Traffic Control Plans in Raleigh, NC

Traffic control and pedestrian plans for work on Raleigh streets and NCDOT roads in Wake County.

Plans for work in Raleigh

LADMA Traffic Control draws traffic control plans for contractors, utilities and property owners working in Raleigh. We cover lane and shoulder closures, sidewalk closures with pedestrian detours, full road closures with detours, and utility and fiber work.

You send the location and the scope. We draw the plan to the standards the reviewing agency uses and deliver it as a PDF you can attach to your permit application.

In Raleigh the City reviews work on every street inside its jurisdiction, including NCDOT streets. On state streets you need both the City permit and the NCDOT encroachment.

Pedestrian detour beside a sidewalk closure
Pedestrian detour beside a sidewalk closure. LADMA field crew at work in the Mid-Atlantic.

Who reviews traffic control plans in Raleigh

Road or topicWho reviewsWhat to know
City streetsRaleigh Transportation, Right of Way ServicesRight of Way Occupancy Permit, filed in the Permit and Development Portal
State-maintained roadsNCDOT Division 5 (Durham, Franklin, Granville, Person, Vance, Wake, Warren)Encroachment Agreement, plus the City permit with a copy of the NCDOT encroachment
Permit typesRight of Way ServicesSidewalk occupancy with pedestrian detour, occupying a lane, and temporary full street closure

Plans follow the NCDOT Roadway Standard Drawings, Division 11, Work Zone Traffic Control, and the North Carolina Supplement to the MUTCD. Work in NCDOT right of way needs an Encroachment Agreement, filed online, with the local district office doing the first review.

Local rules to plan around

  • Raleigh requires a Traffic Control and Pedestrian Plan (TCPED). Review takes 4 to 5 business days, and the plan must be approved and a preconstruction meeting held before work starts.
  • On roads with a marked center line, lane closures are not allowed 6 to 9 AM and 4 to 7 PM, Monday to Friday.
  • Full street closures are submitted at least two weeks ahead. Night work is permitted five business days ahead.
  • A notice letter or door hanger must reach affected neighbors at least 5 days before work.
  • No work during the City holiday schedule or near a scheduled event.

Current work zones in Raleigh include the New Bern Avenue bus rapid transit line, downtown water and sewer upgrades, and NCDOT's Complete 540 project.

Office names, forms and lead times change. Confirm the current rules with the agency before you apply.

What to send for a quote

  • The address, or the road and the nearest cross streets
  • What is being closed: lane, shoulder, sidewalk or the full road
  • Work hours, and whether the work is by day or by night
  • How many days the closure will be in place
  • Any comments you already have from the reviewing agency

See also traffic control plans in North Carolina, our guide to state DOT plan requirements, and how long a plan takes.